MISSION: STS-112 -- 15th ISS Flight (9A), ITS S1 

Vehicle Atlantis/OV-104
Target Launch Date October 2, 2002 NET
Target Launch Period 2 - 6 p.m. EDT
Target Landing Date October 13, 2002
Mission Duration 11 days
Crew Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

After being installed on the Orbiter Transporter, Atlantis’ was moved yesterday morning to be stacked with the Solid Rocket Boosters and External Tank in preparation for its launch to the International Space Station. After technicians noted a concern in the mid-body regarding movement of the Manipulator Positioning Mechanism that is attached to the Remote Manipulator System in the payload bay, engineers began reviewing information to determine a resolution and if additional work will be necessary. Potential work required can be performed while the vehicle is at the pad.

Technicians have removed and replaced all of the 32 bearings located in the JEL (jacking, equalization and leveling) cylinders and reinstalled the 16 cylinders on Crawler Transporter No. 2. Yesterday, the Crawler was moved to the east refurbishment site and retests with the Mobile Launcher Platform are scheduled to begin today and continue through tomorrow.
 

MISSION: STS-113 -- 16th ISS Flight (11A) - ITS, P1

Vehicle Endeavour/OV-105
Target Launch Date November 2, 2002 NET
Target Landing Date November 13, 2002
Mission Duration 11 days
Crew Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Endeavour’s aft closeouts are continuing in preparation for its upcoming launch to the International Space Station. The Crew Equipment Interface Test (CEIT) is scheduled for this weekend.
 

MISSION: STS-107 -- SPACEHAB/FREESTAR Microgravity Research Mission

Vehicle Columbia/OV-102
Target Launch Date January 16, 2003 NET
Target Landing Date February 1, 2003
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

Nominal processing has been completed in preparation for Columbia’s research mission now scheduled for no earlier than Jan. 16.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

The Orbiter Major Modification (OMM) period for Discovery is under way with radiator removal and nose landing gear retraction. Wire inspections will be performed throughout the entire vehicle during the OMM and began in the crew compartment this week.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

09/06/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director