MISSION:
STS-112
-- 15th
ISS Flight (9A) - S1 Truss Segment |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
October 2, 2002 |
| Target Launch
Period |
2 - 6 p.m. EDT |
| Target Landing Date |
October 13, 2002 |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
Final preparations for Atlantis’ lift-off to the International Space Station continue in work and the payload bay doors were closed for flight last week. Mission managers continue to monitor several tropical storms though none are expected in the KSC vicinity in the near term and no work is being held up as we proceed on schedule for launch. The orbiter’s windows were inspected on Saturday due to a concern
on studs that on are the protective covers. Inspections are complete and good. Aft closeouts are in work today with door installation scheduled for Thursday. Functional preparations for the Extravehicular Mobility Units are in work with installation scheduled for Wednesday.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - P1 Truss Segment |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 10, 2002
NET |
| Target Landing Date |
November 20, 2002 |
| Mission Duration |
11 days |
| Crew |
Wetherbee, Lockhart,
Lopez-Alegria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Endeavour’s aft and mid-body closeouts continue in work. Payload bay doors are scheduled for closeout tomorrow in preparation for rollover to begin final preparations for the upcoming launch to the International Space Station. Adjustments on the Manipulator Positioning Mechanism that is attached to the Remote Manipulator System were complete on Friday. Additional measurements and a functional test are in work today. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003
NET |
| Target Landing Date |
February 1, 2003 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Columbia continues processing in preparation for its research mission scheduled for no earlier than Jan. 16. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| The Orbiter Major Modification (OMM) period for Discovery is under way with radiator removal and nose landing gear retraction. Wire inspections continue and will be performed throughout the entire vehicle during the
OMM. |
|
|
|