MISSION:
STS-112
-- 15th
ISS Flight (9A) - S1 Truss Segment |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
October 2, 2002 |
| Target Launch
Period |
2 - 6 p.m. EDT |
| Target Landing Date |
October 13, 2002 |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |

Final preparations for Atlantis’ lift-off to the International Space Station next week continue in work. Launch countdown preparations continue, aft closeouts continue with doors scheduled for installation today. The Extravehicular Mobility Units also have been installed and checked out. Mission managers continue to monitor several tropical storms though none are expected in the KSC vicinity in the near term and no work is being held up as we proceed on schedule for launch.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - P1 Truss Segment |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 10, 2002
NET |
| Target Landing Date |
November 20, 2002 |
| Mission Duration |
11 days |
| Crew |
Wetherbee, Lockhart,
Lopez-Alegria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Endeavour’s forward and window closeouts continue in work in preparation for rollover to begin final preparations for the upcoming launch to the International Space Station in November. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003
NET |
| Target Landing Date |
February 1, 2003 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Columbia continues processing in preparation for its research mission scheduled for no earlier than Jan. 16. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| The Orbiter Major Modification (OMM) period for Discovery is underway with radiator removal and nose landing gear retraction. Wire inspections continue and will be performed throughout the entire vehicle during the OMM. |
|
|
|