MISSION: STS-112 -- 15th ISS Flight (9A) - S1 Truss Segment 

Vehicle Atlantis/OV-104
Target Launch Date October 2, 2002
Target Launch Period 2 - 6 p.m. EDT
Target Landing Date October 13, 2002
Mission Duration 11 days
Crew Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

color video camera mounted on Atlantis' external tankAtlantis on Pad 39BFinal preparations for next week’s launch of Space Shuttle Atlantis to the International Space Station continue on schedule. Launch countdown preparations continue today following the completion of aft compartment closeouts, door installation and confidence checks. Final electrical checks of the External Tank camera are also being conducted today. Mission managers continue to monitor tropical developments though no impacts are expected in the KSC vicinity in the near term and no work is being held up as we proceed on schedule for launch.
 

MISSION: STS-113 -- 16th ISS Flight (11A) - P1 Truss Segment

Vehicle Endeavour/OV-105
Target Launch Date November 10, 2002 NET
Target Landing Date November 20, 2002
Mission Duration 11 days
Crew Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Preparations are in work to begin final preparations for the upcoming launch to the International Space Station in November. Orbiter jackdown and center of gravity checks are complete. The orbiter is scheduled to be mated to the transporter later today.
 

MISSION: STS-107 -- SPACEHAB/FREESTAR Microgravity Research Mission

Vehicle Columbia/OV-102
Target Launch Date January 16, 2003 NET
Target Landing Date February 1, 2003
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

Columbia continues processing in preparation for its research mission scheduled for no earlier than Jan. 16.  Orbital maneuvering system pod functional checks are in work. The payload bay doors were closed yesterday and flow liner weld certifications continue.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

The Orbiter Major Modification (OMM) period for Discovery is underway with radiator removal and nose landing gear retraction. Wire inspections continue and will be performed throughout the entire vehicle during the OMM.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

09/27/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director