|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003 |
| Target Launch
Period |
10 a.m. - 2 p.m. EST |
| Target Landing Date |
February 1, 2003 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| S0007 Launch Preparations began today at Pad 39-A for Shuttle Columbia’s Jan. 16 launch on the Spacehab microgravity research mission. The astronauts and pad workers successfully completed the Terminal Countdown Demonstration Test. Today orbiter aft closeouts are in work along with preparations for the Extravehicular Maneuvering Unit installation, Module Vertical Access Kit storage operations, Mass Memory Unit flight load and Orbiter Midbody Umbilical Unit mate and leak checks. Ordnance is scheduled later this week. No inspections are planned on Columbia related to the BSTRA ball crack evaluation.
|
|
|
|
MISSION:
STS-114
-- 17th
ISS Flight (ULF1) - Crew Rotation/
Multi-Purpose Logistics Module |
| Vehicle |
Atlantis/OV-104 |
| Official Launch Date
and Time |
March 1, 2003 |
| Target Landing Date
and Time |
March 13, 2003 |
| Mission Duration |
12 days |
| Crew |
Collins, Kelly,
Noguchi, Robinson |
| ISS Expedition Crew
7 |
Malenchenko, Kaleri, Lu |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous notes) |
| Atlantis continues to be processed for its March launch to the International Space Station. Today, heat shield installation continues in work as does preparations to install the Forward Reaction Control System. As part of the analysis under way regarding the crack found in the BSTRA ball on Discovery, technicians completed an inspection of Atlantis’ lines and found no cracks. With those inspections complete, all three Space Shuttle Main Engines were installed and leak checks are complete. The Crew Equipment Interface Test is also complete.
|
|
|
|
MISSION:
STS-115
-- 18th
ISS Flight (12A) -- P3/P4 Solar Arrays |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
May 23, 2003 |
| Target Landing Date |
June 3, 2003 |
| Mission Duration |
10 days |
| Crew |
Jett, Ferguson,
Tanner, Burbank, MacLean, Stefanyshyn-Piper |
| Orbital Insertion
Altitude/ Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Deservicing and processing continues for the STS-115 mission to the International Space Station scheduled in May 2003. Throughout the holidays, work continued with waterproofing operations, structural inspections of the orbiter's leading edge and the Forward Reaction Control System. Removal of the Forward Reaction Control System was also completed. Checkout on the Orbiter Maneuvering System Pod is in work as is MEC/PIC verification. Preparations for fuel cell single cell voltage test are also in work. Inspections of the BSTRAs continue on Endeavour to gather data to be used in the analysis of a crack found in an assembly on Discovery. The inspections of Endeavour have found no cracks so far. |
|
|