MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Launch Date |
January 16, 2003 |
| Official Launch Time |
10:39 a.m. EST |
| Target Landing Date |
February 1, 2003 at
9:17 a.m. EST |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| On orbit, Shuttle Columbia continues to perform well on its SPACEHAB microgravity research mission. Columbia’s astronauts completed an experiment studying the activity of bone cells in microgravity and began final tests with a technology demonstration designed to investigate the behavior of capillary-pumped loops in space The 16-day international science mission is scheduled to land on Feb. 1 at 9:17 a.m. at Kennedy Space Center’s Shuttle Landing Facility.
|
|
|
|
MISSION:
STS-114
-- 17th
ISS Flight (ULF1) - Crew Rotation/
Multi-Purpose Logistics Module |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
March 1, 2003 |
| Target Landing Date |
March 13, 2003 |
| Mission Duration |
12 days |
| Shuttle Crew |
Collins, Kelly,
Noguchi, Robinson |
| ISS Expedition Crew
7 |
Malenchenko, Kaleri, Lu |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous notes) |
| Technicians have completed all processing and closeouts in preparation for Atlantis launch to the International Space Station in March. The Orbiter will be weighed today in preparation for mating to the Orbiter Transporter System on Tuesday.
|
|
|
|
MISSION:
STS-115
-- 18th
ISS Flight (12A) -- P3/P4 Solar Arrays |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
May 23, 2003 |
| Target Landing Date |
June 3, 2003 |
| Mission Duration |
10 days |
| Crew |
Jett, Ferguson,
Tanner, Burbank, MacLean, Stefanyshyn-Piper |
| Orbital Insertion
Altitude/ Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Processing continues for Endeavour’s STS-115 launch to the International Space Station in May. The left Orbiter Maneuvering System pod has been removed. Replacement of window No. 11 is in work. Installation of the Endeavour’s Auxiliary Power Units is in work. |
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| The Orbiter Major Modification (OMM) period for Discovery continues with Avionics Bay 3A structures modifications, and Avionics Bay 1 and 2 integrated wiring modifications. Multi-Purpose Logistics Module dedicated heat exchanger and radiator isolation modifications are in work. Wire inspections and repairs are ongoing. |
|
|